EPS@ISEP | The European Project Semester (EPS) at ISEP

Differences

This shows you the differences between two versions of the page.

Link to this comparison view

Both sides previous revisionPrevious revision
Next revision
Previous revision
log [2014/06/12 00:52] – [Weekly Report] team3log [2014/06/23 02:16] (current) – [Activities] team3
Line 98: Line 98:
   * Putting everything together for the Final Report   * Putting everything together for the Final Report
   * Making pictures and video clips for the video   * Making pictures and video clips for the video
 +
 +**14th Week report**
 +
 +  * All the materials arrived except the engine, that is out of stock
 +  * Composing the final presentation and rehearsing for it
 +  * Making the video
 +  * Building the prototype in workshop
 +
 +**15th Week report**
 +
 +  * Building the prototype in workshop
 +  * Making the user manual
 ====== Meetings ====== ====== Meetings ======
  
Line 331: Line 343:
  
   * Powershop in Maia was willing to help us with our materials, but now a week later they replied that it was impossible to order from hobbyking. So we are missing 2 components: battery and motor. Our idea was to use the battery and the engine from an existing product. Is it still possible? We would use the arduino and motor driver, and everything else would be done as previously planned.   * Powershop in Maia was willing to help us with our materials, but now a week later they replied that it was impossible to order from hobbyking. So we are missing 2 components: battery and motor. Our idea was to use the battery and the engine from an existing product. Is it still possible? We would use the arduino and motor driver, and everything else would be done as previously planned.
 +
 +**Minute:**
 +  * Supervisors found us a battery and suggested to order an alternative engine from Inmotion.
 +
 +==== 15th Meeting (2014-06-19) ====
 +  * Final presentation and assessment
 +
 +**Minute:**
 +  * Got feedback from all the supervisors and list of mistakes that have to be corrected for next Thursday.
  
 ====== Activities ====== ====== Activities ======
Line 349: Line 370:
 | 26.03 | 26.03 | Material list | Upload the material list | Team 3 | | 26.03 | 26.03 | Material list | Upload the material list | Team 3 |
 | 26.03 | 30.03 | Marketing Analysis | Working on the Marketing Analysis  | Yvonne, Benedicte, Rauno | | 26.03 | 30.03 | Marketing Analysis | Working on the Marketing Analysis  | Yvonne, Benedicte, Rauno |
-| 26.03 | 31.03 | Ethics | Working on Ethics and Deonthology | Iain | 
 | 26.03 | 03.04 | Sketches| Making representative sketches to visualize the intention | Benedicte | | 26.03 | 03.04 | Sketches| Making representative sketches to visualize the intention | Benedicte |
-| 29.03 | 29.03 | Logbook | Updating logbook | Yvonne, Benedicte +| 29.03 | 29.03 | Logbook | Updating logbook | Yvonne | 
-| 31.03 | 31.03 | Marketing Analysis | uploading the Marketing Analysis  | Yvonne, Benedicte +| 31.03 | 31.03 | Marketing Analysis | uploading the Marketing Analysis Benedicte, Yvonne | 
-| 02.04 | 02.04 | Gantt | uploading the Gantt Chart | Yvonne | +| 02.04 | 02.04 | Gantt | making and uploading the Gantt Chart | Yvonne | 
-| 04.04 | 04.04 | Ethics | filling out the rest of the ethics: marketing,academic,intro and conclusion | Benedicte |+| 04.04 | 04.04 | Ethics | Ethics section | Benedicte |
 | 05.04 | 05.04 | Introduction | Writing the introduction | Benedicte, Yvonne | | 05.04 | 05.04 | Introduction | Writing the introduction | Benedicte, Yvonne |
 | 05.04 | 05.04 | Design | making frontpage and leaflet in photoshop | Benedicte | | 05.04 | 05.04 | Design | making frontpage and leaflet in photoshop | Benedicte |
Line 362: Line 382:
 | 16.04 | 06.04 | Aerodynamics | Meeting with Fernando | Iain, Rauno | | 16.04 | 06.04 | Aerodynamics | Meeting with Fernando | Iain, Rauno |
 | 24.04 | 24.04 | Aerodynamics | Meeting with Fernando | Iain, Rauno | | 24.04 | 24.04 | Aerodynamics | Meeting with Fernando | Iain, Rauno |
-| 29.04 | 29.04 | Project Development | Updating Project Developement | Rauno | +| 29.04 | 29.04 | Project Development | Updating Project Development | Rauno | 
-| 29.04 | 29.04 | Project Management | Topics 1-| Yvonne, Rauno | +| 29.04 | 13.05 | Project Management | Topics 1-4,6 | Yvonne 
-07.05 | 07.05 | 3D  | Working on the driving mechanism | Yvonne |+| 29.04 | 13.05 | Project Management | Topics 5,8 | Rauno | 
 +29.04 | 13.05 | Project Management | Topics 7,9,10 | Benedicte | 
 +| 01.05 | 12.05 | Marketing   | Marketing Mix and rest | Yvonne | 
 +| 01.05 | 07.05 | 3D  | Working on the driving mechanism | Yvonne | 
 +| 07.05 | 07.05 | SW  | Technical drawings | Yvonne |
 | 08.05 | 08.05 | Material List | Last version uploaded | Team 3 | | 08.05 | 08.05 | Material List | Last version uploaded | Team 3 |
-13.05 | 13.05 | Project Management Topics 4-6 | Yvonne, Rauno +08.05 | 20.05 | Sustainability Sustainability section | Yvonne | 
-13.05 | 13.05 | Ethics | Finishing homework | Iain | +15.05 | 20.05 | Sustainability Lifecycle analysis | Rauno |
-| 14.05 | 15.05 | Logbook Updating logbook | Rauno |+
 | 20.05 | 20.05 | Project Management | Topics 7-9 | Team 3 | | 20.05 | 20.05 | Project Management | Topics 7-9 | Team 3 |
 | 21.05 | 21.05 | Ethics | Making the presentation | Yvonne | | 21.05 | 21.05 | Ethics | Making the presentation | Yvonne |
 | 22.05 | 22.05 | Ethics | Presentation | Team 3 | | 22.05 | 22.05 | Ethics | Presentation | Team 3 |
-| 22.05 | 22.05 | Project Development | Shaping the foam body | Yvonne, Rauno | +| 22.05 | 22.05 | Project Development | Shaping the foam body | Rauno, Yvonne 
-| 23.05 | 23.05 | Aerodynamics | Meeting with Fernando to present our ideas | Yvonne, Rauno |+| 23.05 | 23.05 | Aerodynamics | Meeting with Fernando to present our ideas | Rauno, Yvonne |
 | 24.05 | 25.05 | 3D | Making the body in Solidworks | Yvonne | | 24.05 | 25.05 | 3D | Making the body in Solidworks | Yvonne |
-| 27.05 | 27.05 | Communication | Feedback and comments from Ana | Yvonne, Benedicte |+| 27.05 | 27.05 | Communication | Feedback and comments from Ana | Benedicte, Yvonne |
 | 28.05 | 28.05 | Materials | Visiting the Aerokit store in Espinho | Rauno, Iain | | 28.05 | 28.05 | Materials | Visiting the Aerokit store in Espinho | Rauno, Iain |
 | 30.05 | 31.05 | Project Development | Improvements | Rauno | | 30.05 | 31.05 | Project Development | Improvements | Rauno |
Line 382: Line 405:
 | 03.06 | 03.06 | Project Management | Making the presentation | Yvonne | | 03.06 | 03.06 | Project Management | Making the presentation | Yvonne |
 | 02.06 | 12.06 | Materials | Negotiations with "middleman" to order our materials | Rauno, Iain | | 02.06 | 12.06 | Materials | Negotiations with "middleman" to order our materials | Rauno, Iain |
-| 12.06 | 12.06 | Project Management | Presentation Team 3 |+| 11.06 | 11.06 | Gantt | Making the Gantt Chart | Yvonne | 
 +| 12.06 | 12.06 | Project Management | making the presentation | Yvonne | 
 +|  |  | Report | Abstract | Iain | 
 +|  |  | Report | Paper | Iain | 
 +| 09.06 | 10.06 | Poster | Designing the poster | Benedicte | 
 +| 09.06 | 14.06 | Report | Formatting final report Benedicte |
 | 10.06 | 14.06 | Report | Correcting the language | Iain | | 10.06 | 14.06 | Report | Correcting the language | Iain |
-09.06 | 14.06 | Report | Putting everything together for the final report Benedicte +12.06 | 12.06 | Report | Finished Project development Rauno 
-  |  |  | Team 3 |+01.06 07.06 3D  Renewing the driving mechanism in SW | Yvonne | 
 +| 05.06 | 07.06 | 3D  | Making the shell in SW | Benedicte | 
 +| 15.06 | 16.06 | Materials | Collecting the materials from Manuel and from shops | Rauno | 
 +| 17.06 | 18.06 | Final Presentation | Making the Final Presentation | Yvonne | 
 +| 17.06 | 18.06 | Video | Making the video | Yvonne | 
 +| 17.06 | 25.06 | Prototype | Building the prototype | Team 3 
 +| 21.06 | 26.06 | Final Report | Correcting final report | Benedicte, Yvonne |
QR Code
QR Code log (generated for current page)